Commitments
Record the subcontracts and purchase orders you place on a job, change them with a reason after they're signed, and see committed cost beside actual on the job's budget.
A commitment is money you’ve agreed to spend on a job before the bill arrives: a subcontract with a trade you hire, or a purchase order for material you buy for that job. Open them from Finance › Commitments.
Reading commitments needs the Finance cost permission. Creating and changing them needs Finance write, and voiding one also needs Finance void.
The list
Section titled “The list”The top of the page shows the contract sum of the commitments in view, the changes made since signing, what has been billed against them and what’s left to bill. Void commitments are left out of the money.
Use the views to see open commitments (draft, sent and executed), or one status at a time. Kind, Job and Vendor narrow the list, and Sort orders it by newest, number, contract sum or vendor.
Create a commitment
Section titled “Create a commitment”-
Select New commitment, or open a job’s Budget tab and select New commitment there to start on that job.
-
Pick the kind, the job and the subcontractor or supplier, and give it a short name. Leave Number blank and it’s numbered for you (SC-2026-0001 for a subcontract, PC-2026-0001 for a purchase order).
-
Write the scope, inclusions and exclusions, the retainage percent and the start and finish dates.
-
Add the schedule of values: one line per piece of the contract. Enter an amount, or a quantity, unit and unit cost and the amount is worked out. Code each line to a budget line of the job (an estimate section) so committed cost lands in the right place.
-
Select Create draft.
Send, execute and close
Section titled “Send, execute and close”A draft can be marked sent (out for signature) or straight executed if it’s already signed on paper. Executing asks for the date it was signed.
Only executed and closed commitments count as committed cost. A sent one is still being negotiated.
While a commitment is a draft or sent, you can edit everything with Edit, including its lines. Once it leaves draft, the job, vendor, kind, number and retainage are fixed: void it and enter it again to change them.
Change an executed contract
Section titled “Change an executed contract”After a commitment is executed its lines are frozen. To add or deduct work, select Add a change, give the reason, and add one or more rows. A deduct is a negative amount. Each change is numbered and shows the date, who added it and why. A change can’t be zero, can’t take the contract sum below zero, and can’t be edited or removed later; a mistake is fixed with another change.
You can still move a line to another budget line or cost code with Re-code. That doesn’t change the contract sum.
Void or delete
Section titled “Void or delete”A draft that was never sent can be deleted. Anything past draft is voided instead, with a reason. A void commitment stays on record, says who voided it and why, and no longer counts as committed. A closed commitment can’t be voided.
Committed on the job’s budget
Section titled “Committed on the job’s budget”A job’s Budget tab shows each budget line’s budget, committed and actual side by side. Committed is the open part of executed and closed commitments: the contract less what’s already been billed against it. It is never added into actual cost; it becomes actual as the vendor’s bills are approved.