WIP as of a month end
Look back at the work-in-progress schedule as it stood at the end of a past month, and print or export that month.
The WIP schedule (Finance › WIP) normally shows today: cost, billing and over or under billing as they stand right now. Banks, bonding agents and your accountant usually want it as of a month end instead. Opsidian records every open job’s WIP figures once a month, early in the following month, and you can open any recorded month.
Seeing WIP needs the job cost permissions (Finance cost and Job financials), the same as the live schedule.
Open a past month
Section titled “Open a past month”- Open Finance › WIP.
- Select the date button at the top (it reads Live and today’s date).
- Under Month end, pick a month. Only months that have been recorded are listed.
The page then says As of month end with that month’s last day, and when the month was recorded. The month is in the page address, so a link you share opens the same month. Select Back to live to return to today.
What a month end shows
Section titled “What a month end shows”- Contract, change orders, cost, budget, percent complete, earned, billed, retainage held and margin are the figures recorded for that month. Costs or invoices entered later don’t change them.
- Each job’s status is its status at month end. Its number, name, client, location and project manager are shown as they are today.
- The views, filters, search and sort work as they do on the live schedule. Ends this month means jobs scheduled to end in that month.
- A month end is read-only. Needs your move and the row buttons (Bill now, Book cost, Fix estimate) only appear on the live schedule, and so do invoice links and the retainage reconciliation.
- The margin line under each job compares against the month recorded before it.
If a month was never recorded (before Opsidian started recording, or a month that hasn’t been recorded yet), the page says so instead of showing zeros.
Print or export a month end
Section titled “Print or export a month end”With a month end open, Download WIP schedule prints that month: the PDF says As of month end with the date, and when it was generated. CSV of this view exports the same month. Both need the Export finance data permission, and both are recorded in the audit log.