Needs scheduling
Find the work days no crew is booked on, book several days for a crew in one go, and give dateless jobs their dates.
Schedule → Needs scheduling lists every active job with a work day (Monday to Friday, inside the job’s own dates) that no crew is booked on. Rows are grouped by the week the gap falls in.
Export the queue
Section titled “Export the queue”Export downloads the rows you are looking at: the same view, filters, search and sort. Each row has the week of the gap, the job, the client, the uncovered days, the job’s dates, the default crew, how many days are covered and the walkthrough state; contract and not-booked dollars are included only for people who can see job money. It needs the Export schedule lists permission, and every export is recorded in the audit log.
On the main Schedule page, the Month and Agenda tabs have their own Export: the calendar events in the month on screen, narrowed by the status and people filters. Each row has the title, type, status, start and end, location, the crews and people on it, and the job if you can see jobs company-wide. Notes and meeting links never leave. Events you cannot see on the calendar are not in the file.
Book several days at once
Section titled “Book several days at once”-
On a row, choose Book days… (or Book Mon… when the gap is one day).
-
Pick the days. Days already booked, or outside the job’s dates, can’t be picked.
-
Pick a crew. Crews with the most of your picked days open come first, then the job’s default crew, then Rook’s pick. The bar beside each crew shows its week: filled is booked, red is double-booked, empty is open.
-
Check the start and end. They start from the crew’s usual crew-day.
-
Read the check under the times: overlaps, time off, people off shift, the job’s dates and the weather for exactly those crew-days. Warnings don’t stop you. Approved time off needs a reason before you can book.
-
Choose Book N days. Every day is booked in one save, linked to the job and the crew.
The save checks the schedule again. If it refuses (for example, approved time off with no reason), nothing is booked and the dialog lists the days it refused.
To book a whole week, use Book N days… on the week’s heading. Each job starts with its default crew; change a crew, drop days, and book them all in one save. A job without a crew is left in the queue.
Drag a job onto Week by crew
Section titled “Drag a job onto Week by crew”On a computer, the Needs scheduling card beside Schedule → Week by crew works the same way with drag and drop.
-
Hold the handle at the left of a job and drag it onto a crew’s day on the board.
-
While you hold it over a day, a card shows what the schedule says about that crew-day: overlaps, time off, people off shift, the job’s dates and the weather. Nothing is saved yet. Press Esc to cancel.
-
Let go to stage the day. It shows dashed orange on the board, the queue row says where it’s staged, and a bar appears at the bottom of the page. Drop the job on more days, or other jobs, as you like. Dropping a job on a day it’s already staged for moves it to the new crew.
-
Choose Review to see every staged day with its check, set times for a crew with no usual crew-day, give a reason when someone has approved time off, remove a day, or choose whether the crews are told in the field app.
-
Choose Save in the bar. Every staged day is booked in one save, checked by the schedule again. Discard throws them all away.
-
A dialog says what was saved, how many people were told, and where the week now stands. Undo all takes the whole save back in one step: moved days go back, new days are canceled, and the crews are told. If someone changed one of those bookings since, nothing is undone and the dialog says so.
When the card shows an overlap or approved time off, it also names a crew that’s open that day: Try Crew C instead. Drop there, or stage it where it is and choose Try … instead in Review.
Staged days stay staged if you reload the page or come back to the same week later in the same browser session. They’re yours only: nobody else sees them until you save.
Move a booked crew-day
Section titled “Move a booked crew-day”Drag a crew-day that’s already on the board to another crew or another day. It’s staged like a new one: the booking stays where it is, marked Moving, and shows dashed at its new place until you save. A booking that spans several days moves all its days together. Drop it back where it was to take the move away. If someone changes that booking before you save, the save is refused and the board is read again, so you can drag it again from where it now is.
If the save is refused, nothing is booked and the staged days stay where they were, marked Refused. A job whose client is marked do not service can’t get new crew-days: remove its days, or clear the mark on the client first.
Clicking the handle, or pressing Enter on it, opens Book days for that job instead. On Week by crew, Stage adds the picked days to the staged bar, saved with everything else when you choose Save. On a phone the handle is a Book days button. To move a booked crew-day without dragging, open it and choose Edit.
Jobs with no dates
Section titled “Jobs with no dates”The No dates view lists active jobs with no planned start or end. They can’t show in the other views because the queue doesn’t know which days they cover. Filter by what’s missing, default crew, status, client or branch, and sort by how long they’ve waited.
Choose Set dates… to give a job its planned start and end. It then moves to the other views with its open work days.