Production quantities
Record how much work went in each day by cost code, and see percent complete, earned hours, productivity and earned value against the plan.
Production quantities are how much work is in place on a job, counted in the unit the work is measured in: cubic yards of excavation, linear feet of pipe, square feet of paving. Your foremen record them by cost code and work day, and the job’s Production tab compares them with the plan.
Record a quantity
Section titled “Record a quantity”-
Open the job and choose the Production tab. Choose Record quantity (or the + on a cost code’s row).
-
Pick the cost code, enter the quantity, check the unit, and set the work date (today or earlier).
-
Add a location (“Level 2 east”) or a note if it helps. Choose Record quantity.
If you are entering a count someone else gave you (a foreman calling it in from site), pick them under Reported by and say why. Both names are kept. Only people who can edit jobs can enter a count for someone else.
Correct or remove a count
Section titled “Correct or remove a count”A count is never edited in place. In the Quantity log, choose Correct to enter the right figure with a reason: the old count is kept as history and the new one replaces it. Choose the bin to remove a count entered by mistake, with a reason; it stops counting and stays in the history with your name.
You can correct or remove a count you reported or entered. People who can edit jobs can change any count.
The With history view shows replaced and removed counts, and the history button on a count shows every version of it, oldest first.
Read the Production tab
Section titled “Read the Production tab”By cost code shows, for each code on the job:
- Budget: the quantity the work is measured against. It comes from the estimate (the lines coded to that cost code, in the code’s unit) unless a PM set it.
- Installed and Complete: what’s in place, and installed ÷ budget. It can pass 100%.
- Hours budgeted and Earned: the labor plan for the code, and percent complete × that plan.
- Actual, Factor and Earned value, if you can see job costs: the labor hours posted to the code, earned ÷ actual hours (above 1.00 is ahead of plan), and the code’s budget × percent complete.
The figures at the top add the codes up. Productivity for the whole job compares earned hours with every labor hour posted to the job, including hours not yet tied to a cost code.
Set a production budget
Section titled “Set a production budget”When the estimate doesn’t carry the right quantity for a code (it was priced as a lump sum, or the plan changed), choose the sliders button on the code’s row. Enter the budgeted quantity and unit, the budgeted labor hours, or both, and a reason. Leave a field empty to keep the estimate’s figure. Use the estimate puts the code back. Every change is kept with who made it.
You need permission to revise job budgets to set a production budget.
Ask Rook
Section titled “Ask Rook”Rook can list a job’s quantity log and read its production figures: try “How far along is excavation on this job?” or “Which cost codes are behind plan?”