Potential changes

Log a change on a job the moment it comes up, price it line by line with your subs' quotes, and turn it into a change order for the owner to sign.

A potential change is extra work, or less work, that has come up on a job but isn’t agreed yet: the owner asks for a wider patio, the crew hits rock, an inspector wants a different detail. Log it the day it comes up, price it, and turn it into a change order when it’s ready for the owner.

Potential changes that are still open count as pending. Pending is shown beside the contract, budget and cost, never inside them: only a change order the owner accepts moves the contract.

  1. Open the job and choose the Change orders tab. The Potential changes card sits above the change orders. Choose New potential change.

  2. Give it a title the owner would recognize, and say what changed.

  3. Pick the scope (In scope, Out of scope or To be decided) and the reason.

  4. Say who has the ball in court (who owes the next move: us, the owner, the architect, a subcontractor) and when it’s due. When it’s on your side you can name the person.

  5. Enter a rough price to the owner, and a rough cost to you if you can see job costs. Choose Add potential change.

Each potential change gets its own number on the job (CE-001, CE-002…) and its own page.

On the potential change’s page, the Priced lines card holds the price line by line. Choose Add line, then give each line a description, type, quantity, unit and unit cost, and optionally a cost code and a sub. Choose Save and price lines: Opsidian prices every line under the job’s contract terms, so the price matches what the change order will show.

Once a line has a sub, record their quote on it:

  • Ask for a quote marks the quote as requested. Nothing is emailed: you ask the sub yourself.
  • Record their quote enters the lump sum they sent you. It becomes the line’s cost.
  • They declined records that the sub won’t quote.

Until it has lines, a potential change counts at its rough price.

The Next move card offers only the moves that make sense from where the potential change is:

  • Start pricing while you collect costs and quotes, or Reopen to go back.
  • Send for approval once it’s priced and waiting on the owner.
  • Mark approved or Mark rejected when the owner decides. A rejection asks why.
  • Void withdraws it if it was logged in error or never happened. Void asks why, and a voided potential change can’t come back.

Every move, edit and quote is kept on its History with who did it and when.

When it’s priced, choose Create change order. Opsidian builds a change order on the job’s contract from its lines and moves the potential change to Pending approval. Send the change order’s proposal as usual. From then on the potential change follows its change order: accepted, it’s approved; declined, it’s rejected.

If you wrote the change order first, choose Link a change order on the potential change instead.

A change order needs the job’s estimate to be accepted first. If it isn’t, Opsidian says so on the Create change order row.

The job’s Budget and WIP tabs show a Pending changes card: how many potential changes are open, what the contract would be if they’re all approved, what the budget would need, and the over/under. Choose See them to jump to the list, filtered to the pending ones.

On the list, filter by Status and Ball in court, or search by title, description or number.