Progress billing
Bill a job in stages. Set up its schedule of values, then create pay applications against it.
Contract jobs are often billed in progress payments rather than one invoice at the end. In Opsidian that’s two pieces, both reached from a job’s Billing tab: the schedule of values, the contract broken into scope lines, and pay applications (AIA G702 / G703), each billing the work completed to date against those lines.

Set up the schedule of values
Section titled “Set up the schedule of values”A job that bills by invoice shows a Progress billing card on its Billing tab with Set up schedule of values.
-
On the job’s Billing tab, choose Set up schedule of values. Later, open it from the tab’s Schedule of values section or the job’s ⋯ menu.
-
Enter the Original contract and set the Default retainage. Accepted change orders add to the Contract sum; when new ones are accepted, the page offers Update contract sum to bring them in. A change order that is still a draft or proposed isn’t in the contract sum and can’t be billed.
-
Add your scope lines. If the job came from an estimate, Import from estimate makes one line per estimate section; otherwise choose Add line and give each a description and a Scheduled value, with an optional per-line Ret. % override. Lines total shows how the lines compare to the contract, and Against estimate compares each line to the bid.
-
Choose Save schedule.
Once a pay app has billed the schedule, a change saves a new version: you’re asked Why is this changing?, and the earlier version stays under History. Pay apps from then on bill the new version.
Bill a period
Section titled “Bill a period”-
Choose New pay app on the job, or New pay app #2 (with the next number) on the schedule of values. It’s available while the schedule is Active.
-
On the Continuation sheet (G703), enter what happened this period per line: This period (work completed) and Stored (materials on site, not yet installed). You can type it as a $ amount, % to date or % this period. Previous, Completed, %, Balance and Retainage update as you type.
-
The figures card above it is the G702 summary: Contract sum to date, Completed & stored, Retainage held, Previous certificates, Current payment due and Balance to finish.
-
Choose Create pay app #1 (with its number). The draft is saved and its own page opens, where you review it and move it through Draft, Approved, Sent to AP and Paid (with Owner review when the job needs it). Nothing goes to the client until you send it.
Retainage
Section titled “Retainage”While retainage is held, the Billing tab offers Release retainage, which prepares a final draft invoice for the held amount, again for you to review and send. If closeout items are still owed on the job, it shows Open closeout instead, because retainage releases after them.
Good to know
Section titled “Good to know”- The Billing tab lists Pay applications, Invoices, the Schedule of values, Payments and Retainage, and filters invoices by Unpaid, Overdue, Paid, Pay apps and Draft.
- A retainage release appears in the list as Retainage release.
- A pay app that needs a lien waiver says so on the Billing tab, with Attach on the pay app.
- The P&L and WIP tabs on the same job show profitability and work in progress for roles with cost visibility.